This note describes the Thameslink infrastructure project, including information on how the scheme got off the ground, construction issues and the policy of successive government towards the project. It does not deal with the controversial Thameslink rolling project to purchase new trains to run on the route. This is covered in HC Library note SN3146. The re-let of the Thameslink passenger franchise is covered in SN1343.

The Thameslink project involves electrification, signalling and new track works. This will increase capacity, reduce journey times and generally expand the current Thameslink route through central London and across the South East of England. On completion in 2018, up to 24 trains per hour will operate through central London, reducing the need for interchange onto London Underground services.

The project dates back to the Conservative Government in the mid-1990s. It underwent a lengthy public inquiry process under the Labour Government and has been continued by the Coalition Government. However, the scheme will not be complete until 2018 – 14 years later than its supporters had hoped when the scheme was initially proposed.


Documents to download

Related posts

  • Open access operators for rail services

    A Westminster Hall debate on 'Open access operators for rail services' is scheduled for Thursday 6 February 2025, from 1.30pm to 3.00pm. The debate will be led by Martin Vickers MP.

    Open access operators for rail services
  • Railway services in the South West

    A Westminster Hall debate on railway services in the South West will be held on Tuesday 14 January 2025 at 9:30am. The subject for this debate was determined by the Backbench Business Committee and the debate will be opened by Martin Wrigley MP (Liberal Democrat, Newton Abbot).

    Railway services in the South West